Project Overview


This page provides an 'At A Glance' summary of the status of the project, with due dates and action summaries for all members of the team, as well as a financial summary.

Project

Name/ Number:

Interstitial Home Page

0020-01

% Complete

21%

Launch Date

4/29/01

Client

To Do:

Here you will find a detailed TO DO list of items that need your attention, such as approvals and content submission.

Review first concept of home page, call or email feedback

Status:

Completion Date:

Submit content to legal

Status:

Completion Date:

Supply text for intro paragraph

Status:

Completion Date:

Next
Steps:

Here you will find the next steps that need to be taken on the project.

 

Below you will find detailed financial information on your project, including estimates, cost-to-dates, and invoices issued to date.

Estimates:

Date

Estimate Number

Amount

Status

4/16/01

0020-01-01

$ 8,771.00

Initial approved estimate

5/4/01

0020-01-02

$ 583.00

Incremental Estimate for change in scope. Awaiting approval

Cost-to-Dates:

Date

CTD Number

Amount

Status

4/23/01

0020-01-01

$ 1,072.00

Cost-to-Date #1

4/30/01

0020-01-02

$ 1,879.00

Cost-to-Date #2

 

 

$ 5,820.00

Budget not used to date

Invoices:

Date

Invoice Number

Amount

Status

4/16/01

0020-01-01

$ 4,385.50

50% Pre-billing. Due 5/16/01.